2018 QAI Process
The 2018 QAI process will change slightly when it comes to shutting off DUCs, please review the steps below.
- No more re-inspections by 2M
- Production Manager required to re-inspect all failed houses (Prior to PSD)
- If house is considered complete by PM prior to PSD, HR 2.2 Attachment B (Adjustments to DUCs) process can be used to calculate DUC end date for PJM bonus
Please direct all questions to Jason Leydig Jleydig@nvrinc.com
Step-by-step guide
- House Fails inspection.
- Users are notified of failure via Precision, a link to the report will be in the email.
- Status of QAI inspection will be visible on Schedule Summary Page, it will now read Pass or Fail after an inspection.
- Opening a schedule will show a completed QAI task with new task called "QAI PM Sign-off" in RED
- Clicking on the task will display the a link to the QAI report and Punchlist tab (NEW)
- Clicking on Punchlists will display all items on QAI report, a user can also click on the QAI report to view the PDF.
- PM to walk house and complete task when they feel it is ready for a Homeowner to see it
- Task can be completed via web or mobile app, link to report or punchlist currently not available via mobile app.
- PM is only person who can complete task
- PM is able to request a Stop Days Adjustment to DUC if they feel the house is ready PRIOR to the PSD date, if not PSD date will be used for bonus purposes.
- If you decided to stop the days please select the QAI PM Sign Off, this date on this form should mirror the date of the task in the schedule.
- End of DUC task should be on the same date