Phase Completion

Overview:

Leveraging completed tasks in SchedulePro to release payment on non-excluded phases of construction.

Schedule Pro tasks should be completed by Project manager when work is 100% complete

Non-Excluded phases are defined in UCS (by corporate) and will block a deposit date for a posted invoice without a completed task in schedule pro.

The 30 day (or different if negotiated) payment terms start upon the latter date of

  1.  Invoice receipt date (based on weekly Friday cutoff)
  2.  SchedulePro task completion date

Phase Completions will be sent from SchedulePro to UCS once per day.  The Open Invoices screen on the Vendor record will be updated with a PhAct Status of “OPEN” or “COMPLETE”.  Invoices with an “OPEN” status will not have a Deposit Date.   Invoices that have phases that are in the exclusion list will not have a status.