The purpose of this task was to schedule the installation of property fence.  These task was needed because it occurred at a different time then other activities.  This task is not required and is available to all divisions.  It is currently setup as a COMMUNITY option. If interested in using this new task and option please contact your Area Lead.

If this task is used it will increase the duration of the phase and could potentially delay payment of any PO created for 456K


Task Name: Install Fence

Phase : 456K

Option Driven : Community

Optional : Yes


Request originated for phase completion by Lisa Fox


Related content

New Task - Permit Package
New Task - Permit Package
More like this
New Option and New Task | Delivery - LP Trim
New Option and New Task | Delivery - LP Trim
More like this
New Option and New Task | Hardwood Landing
New Option and New Task | Hardwood Landing
More like this
New Task | Exterior Concrete
New Task | Exterior Concrete
More like this
New Option and New Task | Metal Coping
New Option and New Task | Metal Coping
More like this
New Tasks | Foundation Point up and Pier Pad/Beam Pockets
New Tasks | Foundation Point up and Pier Pad/Beam Pockets
More like this