As part of the implementation of our brand promise and to deliver a 100% complete home, we will be adding an additional task “QAI Verification” to coordinate 2M returning to the home. During their return, they will be checking to see if all items discovered during the QAI have been addressed. There will be an exception process where items will be discarded with the approval of certain managers (this process to be outlined at a later date). resolved. PJM should treat the QAI Verification task exactly like the QAI task when it comes to updates and changes to the schedule.

Below are the steps that must be taken to ensure a smooth transition into using this task.

*The term PDS “PDS (Customer Meeting)refers to the New “New Home Orientation (NHO). We will be changing the name in the system to NHO at a future date

Existing Schedules with a QAI scheduled for 2/17 or later

On 1/16 15 at 6pm we will be manually adding the “QAI Verification” task to any schedule with a QAI date of 2/17 or later. The task was will be placed on the same day at as the QAI.

Actions needed

  • QAI Verification will need to be placed 5 moved so that there are 4 Business Days after QAI datePDS between it and the QAI to allow you time to resolve all items.

  • PSD (Customer Meeting) task to be placed 1 day after QAI verification Verification

  • Settlement task to be placed 2 days after PSD (Customer Meeting)

Note

IMPORTANT

A passing QAI still shuts off DUC, failing the QAI will revert to the PSD to stop days unless a Stop Days Request is approved.

If your QAI slips after 2/17 you do not needed need to add the QAI Verification task

If you have communicated to your customer their New Home Orientation date or their Settlement date is set, you do not need to update

Image Removed

.

Division Managers will determine if/when NHOs and Settlement dates should be moved

Image Added

Existing Templates

On 1/16 15 at 6pm we will be manaully manually adding the “QAI Verification” task to ALL TEMPLATES. We will be making the following updates.

  • QAI Verification will be added 5 DUCs after the current location of your QAI taskplaced so there is 4 days between it and the QAI

  • PSD (Customer Meeting) will be moved to 1 Day day after the QAI Verification task

  • Settlement will be moved to 2 days after the PSD (Customer Meeting) task

...

Note

IMPORTANT

You should update your templates as soon as possible. As new schedules are created, they will use this same sequence and require you to make updates in your schedule. Updating your templates will decrease the amount of work required in the long term work required.